Part of the southbound outside lane of Brentwood Boulevard will be closed Monday at 5:30 a.m. for the St. Louis County project to resurface the road and replace associated concrete work, the city reported Saturday.
- Krupp will now be closing the southbound outside lane starting at 5:30 am Monday morning between Harrison and Manchester.
- The right turn lane from eastbound Litzsinger Road onto Brentwood Boulevard closed until next Monday, August 17.
- Krupp will continue working on ADA ramps and sidewalk.
- During work hours, the contractor is allowed up to a 15 minute delay.
The city of Brentwood also reports that West Contracting has completed the asphalt overlay on the following streets:
- High School Drive
- Annalee Avenue
- Tilles Drive
- Louis Avenue
Also from the city: Lawn, Pine Ave. (8700 block), Spanish, Urban Dr., Woodsey Dr. Asphalt Project Update:
- Aug. 13 – Missouri American Water Company repaired a small leak on Pine Avenue
- Aug. 14 – Brentwood Public Works poured a concrete base
- Aug. 17 – West Contracting is scheduled to complete paving the area on Pine.
The city also reports that Public Works will begin sidewalk repairs along Rosalie Avenue on August 19.
See more information and photos from the above projects at: “Capital Improvement Projects.”